Role: Health & Safety Advisor
Project: Canopies and station structures to 15 DLR stations throughout south east London.
We were employed as a health and safety advisor to a key sub-contractor on the DLR, their tasks was to install all the new station platform canoipes and cladding. The works weere carried out mainly during engineering hours and involved significant amounts of craneage throughout. The project took over two years to complete. We were required to produce all health and safety documentation relating to the works opertation and seek approval from the Principal Contractor and DLR.
Duration: 24 months
Date: complete September 2009